1942 – DC-3A

general updates – march 12, 2025

The Spirit has returned from a successful west coast trip.


general updates – february 20, 2025

A post-maintenance test flight has been completed.


general updates – february 18, 2025

Post-inspection engine runs have been completed.


general updates – february 6, 2025

The replacement of the vertical stabilizer de-ice boot is in progress.


return from france – september 11, 2024

N8336C has safely returned to UAO from France following the engine change in Dole.


engine change – june 19, 2024

The spare engine has been crated and shipped to Dole.


General Updates – may 15, 2024

After a series of shakedown and crew currency flights, N8336C has departed UAO for the D-Day 80th events on the East Coast prior to making the North Atlantic crossing.


general updates – april 18, 2024

The A1 and B3 inspections are wrapping up and discrepancies are in work. The SatPhone has been ops checked.

general updates – april 3, 2024

The A1 check and the B3 Inspection are underway prior to the Normandy trip.


general updates – march 6, 2024

The “Spirit of Douglas” livery has been installed, and the aircraft has completed another test-flight coming out of the avionics work scope.


general updates – february 28, 2024

The aircraft has successfully completed several test flights coming out of the avionics upgrade and A-checks. Post flight discrepancies are now in work. The 91.411 and 91.413 IFR certifications are complete, the pitot static system is very tight. New livery installation is in work.


avionics upgrade and a-checks – february 21, 2024

Work on the remaining discrepancies from the A-checks is nearly complete. The interior is being reinstalled in the flight deck and companionway. Avionics have been powered up and are undergoing calibration.


avionics upgrade and a-checks – february 7, 2024

Work on the ship’s electrical to accommodate the new panel layout and avionics continues. Work on the discrepancies found during A-checks is wrapping up.


avionics upgrade and a-checks – january 31, 2024

Discrepancies found during the A-checks are now in work. The mounting bracket for the magnetometer in the wing is being installed. Modification of the existing ship’s electrical system to align with the new panel layout is the most significant part of this project. This aspect of the work is well underway, and we hope it will be completed prior to the end of next week.

avionics upgrade – january 25, 2024

Work continues on the avionics upgrade. The overhead instrument backing panels have been installed. The main instrument panel has been installed and instrument installation has started. Wires are being run for the cabin phone and other avionics systems.


avionics upgrade and a-checks – january 10, 2024

The remaining A-checks are nearing completion (to the extent possible considering the disassembled state of electrical and hydraulic systems associated with the avionics work scope.) A list of discrepancies is being compiled. Work on the overhead instrument panel installation continues. We anticipate the arrival of powder coated and engraved main instrument panels within the next few days.


avionics upgrade, a-checks – january 3, 2024

Main instrument panel attach brackets are being installed. Work continues on the A-check series.


A-Checks – december 2023

Remaining 2023 A-checks are in progress.


Avionics upgrade – december 2023

Main and overhead instrument panels have been test fit. Instruments are being test fit to the panels. The new wiring harness for the avionics is in work.


avionics upgrade – december 2023

Construction of the overhead panels is approaching completion.


avionics upgrade – december 2023

Work continues on preparation for the new wiring. Panel mock ups are being test fit and adjusted as necessary.


AVIONICs upgrade – november 2023

Old avionics and associated wiring bundles are being removed in preparation for the new installation. Work has begun on the mock ups for the new instrument panels.


AVIONICS UPGRADE – November 2023

The old panel has been removed, and the team is working through wire bundles.